# Limit Charge Power -> Optimize Self-Consumption

Initial State: `Limit Charge Power`  
Target State:  `Optimize Self-Consumption`  

## Test Procedure

1. `Grid setpoint` is set to 2500W.
2. The system is brought to the `Limit Charge Power` by activating its option and the `Maximum Charge Power` is set to 1000W.
3. A load of 2000W or more is connected to the system.

## Expected Outcome

As soon as the load is connected, the battery state changes into the `Optimize Self-Consumption` state and charges with power of range (0W-1000W), depending  
on the load power.

## Tested Outcome

The systen reacted as expected.