# Hold min SOC -> Forced EOC

Initial State: Hold min SOC
Target State: Forced EOC

Test Procedure

  1. Min SOC is set lower than the current SOC
  2. Min SOC should be 50% or lower
  3. Grid setpoint is set to a negative value (-2000W)
  4. Wait until the system reaches the Hold min SOC state
  5. activate Force charge now on the remote console

Expected Outcome

As soon as Force charge now is activated, the system changes into the Forced EOC state and charges with high power (min. 1000W)

Tested Outcome

The system reacted as expected and switched from Hold min SOC state to Forced EOC state when Force charge now was activated on the
remote console. The charging power was around 1200W. The were observed power drops during this process.